Our goal is to see first export of LNG by no later than 2030 and sooner if this can be accomplished in a safe and environmentally responsible manner. As per the summary schedule, LNG NL is currently in the early development phases of this project. Our engineering consultants were commissioned and have  since completed the first phase of feasibility and pre-FEED engineering work.

2021
Pre Development Phase
2022
Gate 1 Review (IDENTIFY)
2022
Pre-FEED
Late 2023
Gate 2 Review (SELECT)
2024-2025
FEED
Mid 2025
Gate 3 Review (FID)
2025-2029
Execution - EPC
2030
First LNG
Schedule
Timeline icon red.png
Timeline icon red.png
Concept icon.png
engineering icon.png
execution icon.png

Stakeholder engagement (oil companies, financiers, governments, local communities, Trades NL and service providers, fabrication sites, Indigenous Groups, EPC companies)

Engineering feasibility studies (LNG plant and pipeline constructability, risk analysis, site evaluation, pipeline route evaluation, refined cost estimates)

Preliminary market evaluation and project economics

Gears.png
stakeholder.png
Economics_2.png
Include but are not limited to the following:
Predevelopment Activities

Through early engagement with federal and provincial agencies, LNG NL is developing a comprehensive permitting strategy and a regulatory roadmap with a view to filing a formal Development Application by no later than the first quarter of 2023. Other milestones that must be achieved in order ensure first LNG by 2030 include approval of the Development Application by no later than the first quarter of 2025 and Project Sanction and EPC Contract Awards by no later than the last quarter of 2025.

Detailed Project Schedule